Saeco Newsitems
Newsitem | Details | Date |
---|---|---|
Hyundai Contract | Signed Contract with Hyundai for field testing approximately 10000 Valves for Karan project |
20/11/2010 |
Completed 6 overhauls in SEC-WEST as our first entry into Saudi Aramco market. SAECO was awarded a contract for the rehabilitation of 9 units of Frame 5 gas turbines at ... |
20/11/2010 |
|
SABIC Contract | Signed a 5 year global contract with SABIC for the calibration of instruments for all SABIC affiliates. |
20/11/2010 |
Letter of Award | Letter of award received from Saudi Aramco for 2 major inspections and 2 combustion inspections of gas turbines. |
20/11/2010 |
SWCC Contract | Signed a contract with SWCC for retrofitting project for field instruments at the SWCC Shuqaiq plant. |
21/11/2010 |
JGC Arabia Ltd.Contract | Signed a contract with JGC Arabia Ltd. for the field testing of approximately 6,000 valves for the Manifa Project. |
06/03/2011 |